RAV cost over-runs underscore need for independent oversight, says James



VICTORIA - Today's revelation that the privatized RAV line project is already well over $100 million over budget -- before a single shovel has touched the ground -- provides further evidence that the project needs an independent financial analysis, as previously called for by New Democrats, NDP Leader Carole James said today.

"Construction has yet to begin and this private RAV project is already grossly over-budget," said James. "Premier Campbell has proven that he's incapable of properly managing the construction of the RAV line in the public interest."

James said at a time when people are waiting longer than ever for surgery, and when education funding has been cut, the Premier is allowing the RAV line costs to spiral out of control before it has even started.

"Given that the RAV project gets more expensive every day, what British Columbians need now is straight answers and accountability," said James. "That means the Premier should immediately order an objective, independent financial analysis, through the Auditor General, of what this project will finally cost.

"The Premier is spending millions of public tax dollars to convince British Columbians he's changed, that he now cares about the priorities of ordinary people. But the ongoing mismanagement and cost overruns on the RAV project serve as a reality check for British Columbians about this government's misplaced priorities."

- 30 -

To unsubscribe or change your settings go to: http://www.e-2ve6y.signup.bc.ndp.ca/
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://bcfed.net/pipermail/labcomm/attachments/20041119/9ffde28c/attachment.html>


More information about the LabComm mailing list